Project Status and Readiness Scorecard

Audit date: 2026-11-15. Reported “about 40% complete” is an owner estimate, not a measured engineering result. The estimate below is a transparent reviewer judgment, not a statement of production readiness.

The feature matrix includes the first approved implementation slice. Weighted totals below are the pre-implementation baseline, not a remeasurement of the current worktree.

The project owner has approved the full project polish scope and selected Django/PostgreSQL as the target system of record for catalogue and user data. Catalogue, auth, and matching slices are implemented and committed; authenticated user-data migration and production PostgreSQL verification remain outstanding. Live Google OAuth verification is deferred until credentials are configured securely. See architecture decisions.

Feature matrix

Area Status Evidence and remaining work
Routed landing, explorer, tracker, sources, detail, auth pages COMPLETE for page/routing presence Routes in src/App.tsx; mobile/route smoke tests exist. Feature presence does not imply backend persistence.
Desktop/mobile navigation COMPLETE for tested shell journeys tests/e2e/shell.spec.ts covers route, overflow, and drawer behavior. Full accessibility audit remains.
Student dashboard NOT IMPLEMENTED as a distinct dashboard route The inspected route map has landing, explorer, tracker, sources, detail, and auth pages, but no dedicated student dashboard.
Authentication UI/API PARTIALLY COMPLETE Email/password API handlers and frontend calls exist; E2E covers page links and local mismatch validation, not successful live login. Google OAuth configuration is unverified.
Student profile PARTIALLY COMPLETE UI and authenticated backend profile API exist; SPA stores profile locally instead of using that API.
Catalogue/search/filter PARTIALLY COMPLETE Public Django API reads now drive the landing page, explorer, tracker, and sources page. Profile/saved/tracker persistence is still local.
Scholarship detail PARTIALLY COMPLETE Detail is fetched by canonical slug; loading, 404, server-error, and network-only offline fallback states are implemented and covered by service/E2E tests.
Eligibility explanation PARTIALLY COMPLETE TS and Python deterministic evaluators exist; dual implementations require parity maintenance. Backend evaluation does not load the user's stored profile.
Eligibility criteria coverage PARTIALLY COMPLETE GPA, degree, field, citizenship, English and work-experience rules exist in the TS engine. Income is not modeled; some catalogue income requirements are represented as GPA rules. ECTS, waiver defaults, and some failure explanations need review.
Save/unsave PARTIALLY COMPLETE Backend owner-scoped API exists; inspected client persistence is browser-local.
Application tracker PARTIALLY COMPLETE UI and backend CRUD exist; client data is local and full persistent journey is not E2E-tested.
Error, loading, and empty states PARTIALLY COMPLETE Catalogue/detail/source states distinguish offline fallback, HTTP errors, empty results, and detail 404; broader cross-journey acceptance remains.
External provider navigation PARTIALLY COMPLETE Application and data-driven source links use an HTTPS/domain confirmation gate; allowlist policy and deployed behavior remain unverified.
Django API authentication and authorization PARTIALLY COMPLETE Endpoints and permission classes exist; DB-backed runtime errors and successful OAuth prevent claiming end-to-end verification.
Request validation and API error handling PARTIALLY COMPLETE DRF serializers and validation exist, but response/error contracts and database-backed negative cases are not comprehensively verified.
Backend logging NEEDS REVIEW Framework logging is present, but sensitive-data redaction and production log/alert configuration were not verified.
API documentation PARTIALLY COMPLETE Catalogue summary/detail and rule payloads have SQLite-backed API tests; other response contracts and PostgreSQL runtime behavior remain unverified.
Scholarship ingestion PARTIALLY COMPLETE Staff trigger and collectors exist; all sources/collectors and data reuse rights are not verified.
PostgreSQL schema/migrations PARTIALLY COMPLETE Django models and migrations exist, including the matching ownership migration. Local pytest requires a reachable migrated database; the CI database job has not been confirmed green.
Client database access NOT APPLICABLE The client has no Firebase/Firestore SDK; catalogue and source reads go through the Django API with a bundled offline fallback.
Test/CI coverage PARTIALLY COMPLETE Frontend service/unit, component, Django API, backend unittest, and landing/detail Playwright checks pass locally. Hosted PostgreSQL CI, live services, and several user workflows remain unverified.
Deployment, backups, monitoring NOT IMPLEMENTED / NEEDS REVIEW No deployment target or operational evidence was found.
Indian data coverage/licensing NEEDS REVIEW NSP pages are useful manual leads; open-data feeds and reuse terms remain unresolved.

Transparent completion estimate

Owner-reported 40% was not used as the result. The following weighted rubric is an approximate assessment of the code and tests, where category scores are judgment calls based on the matrix above:

Workstream Weight Implemented estimate Evidence-verified estimate Production-ready estimate
Frontend user journeys 30% 65% 55% 50%
Backend APIs and persistence 25% 55% 30% 25%
Eligibility and data quality 15% 50% 65% 25%
Tests and quality gates 20% 55% 65% 35%
Operations and documentation 10% 25% 20% 10%
Weighted total 100% 54% 49% 34%

Formula: sum of each category's weight × category estimate, divided by 100. The implemented score measures code presence, verified score measures checked behavior/evidence, and production score measures operational readiness. They are not interchangeable, and should be recalculated after agreed acceptance criteria and an instrumented review.

Readiness scorecard

Effort ranges below are approximate person-days and overlap; they are not additive. Cross-cutting test/database work is shared between categories.

Category Observed state Remaining work / priority Effort Dependencies Completion criteria
Functional completeness Main discovery/profile/tracker surfaces exist; some data paths differ. Close the core journey defects. High 3–5 API/data ownership decision (approved) Synthetic user completes discovery → details → match → save → tracker with expected states.
Backend quality APIs/models exist; matching ownership is fixed; PostgreSQL-backed test execution is unverified. Harden validation/permissions and confirm database-backed tests. High 4–7 Disposable PostgreSQL CI CRUD, validation, and cross-user denial pass in database-backed tests.
Frontend quality Routed responsive UI and tests exist; some state is local-only. Integrate API state and test errors/loading/empty states. High 5–8 Backend contracts Reloaded synthetic account retains expected profile/saved/tracker state.
Database PostgreSQL models, migrations, and a seeded 48-record catalogue exist. Verify migrations, constraints, indexes, and backup policy. High 2–4 PostgreSQL test environment Fresh migrations work and selected schema constraints are covered by tests.
Data quality Some public sources exist; Indian coverage/licensing unresolved. Verify sources/cycle/permissions; do not import without approval. High 4–8 Provider/source permission Every published real record has evidence, freshness, reuse status, and manual review.
Security Source rules and API permissions exist; deployed state/negative tests unverified. Emulator/API checks, OAuth/secret/CORS/log review. High 3–6 Staging/test credentials configured privately Negative access tests pass; no production assumptions are made from source-only checks.
Testing Frontend/backend unittest and E2E pass; pytest persistence errors without DB. Add reproducible PostgreSQL and contract test coverage. High 4–7 Disposable DB service CI passes unit, API, migration, and browser suites from a clean checkout.
Performance No controlled benchmark was performed. Define local dataset and measure only after correctness. Medium 2–4 Stable API/database baseline Reproducible benchmark reports method, dataset, and results.
Documentation Current readiness package exists; older documents need reconciliation. Maintain current links and update docs with implementation. Medium 1–3 Code decisions No contradictory implementation claims; current setup/tests verified.
Deployment readiness Hosting, backups, monitoring, rollback unverified. Build secure staging and operational procedures. Low for demo; high before launch 4–8 Hosting choice and private secrets Staging smoke, backup/restore check, alert, and rollback documented.
Academic demo readiness Local UI and smoke suite usable; live API needs DB/OAuth setup. Finish a stable synthetic-data walkthrough. High 2–3 Choose local API-backed versus fallback demo Demo guide works from a clean local setup without real user/provider data.
GitHub presentation README, CI, docs exist; remote configured. Keep CI/docs current and review release policy. Medium 1–2 Authorized PR/release process Required checks pass; claims, licensing, and contribution docs are accurate.

Implementation options

Effort estimates are engineering person-days, excluding waits for external provider permissions or cloud account access.

Scope Estimated effort Main deliverables / dependencies
A — Minimum academic demo 5–8 person-days Clarify profile defaults and local-persistence messaging; curate clearly labelled synthetic scenarios; establish disposable local DB or mock-backed demo boundaries; add journey tests and demo runbook. Depends on choosing local-only versus API-backed demo.
B — Backend engineering depth 12–20 person-days PostgreSQL test setup/CI verification; API request/response/permission coverage; integrate profile/save/tracker API paths; database constraints and ingestion validation/provenance. Depends on DB environment and API/data ownership decision.
C — Full project polish 25–40 person-days Scope B plus reviewed Indian source partnerships/licensing, controlled data refresh, parity/quality suite, accessible UX polish, staging deployment, secrets, backups, monitoring, security verification, full docs and demo packaging. Depends on hosting choice and permission to reuse public data.

Git and inspection boundary

The implementation and documentation changes reviewed here are committed on main locally. No fetch, push, or remote publication was performed during this documentation pass, and hosted CI status was not independently checked. Remote URL credentials are intentionally not reproduced.

Work not performed

Application source code, tests, and documentation were changed. No production configuration, database records, deployed services, or public scholarship records were changed. Manual browser review and live OAuth/API verification were not performed; the E2E run used a mocked catalogue API fixture.